Questions
Job Costs Using a Plantwide Overhead Rate Naranjo Company designs industrial prototypes for outside companies. Budgeted...

Job Costs Using a Plantwide Overhead Rate

Naranjo Company designs industrial prototypes for outside companies. Budgeted overhead for the year was $225,000, and budgeted direct labor hours were 18,000. The average wage rate for direct labor is expected to be $25 per hour. During June, Naranjo Company worked on four jobs. Data relating to these four jobs follow:

Job 39 Job 40 Job 41 Job 42
Beginning balance $24,800 $32,500 $15,400 $1,600
Materials requisitioned 20,400 23,200 10,400 13,400
Direct labor cost 11,500 20,300 5,050 4,300

Overhead is assigned as a percentage of direct labor cost. During June, Jobs 39 and 40 were completed; Job 39 was sold at 125 percent of cost. (Naranjo had originally developed Job 40 to order for a customer; however, that customer was near bankruptcy and the chance of Naranjo being paid was growing dimmer. Naranjo decided to hold Job 40 in inventory while the customer worked out its financial difficulties. Job 40 is the only job in Finished Goods Inventory.) Jobs 41 and 42 remain unfinished at the end of the month.

Required:

1. Calculate the balance in Work in Process as of June 30.

$

2. Calculate the balance in Finished Goods as of June 30.

$

3. Calculate the cost of goods sold for June.

$

4. Calculate the price charged for Job 39. Round your answer to the nearest cent.

$

5. What if the customer for Job 40 was able to pay for the job by June 30? What would happen to the balance in Finished Goods?

What would happen to the balance of Cost of Goods Sold?

In: Accounting

Job Costs Using a Plantwide Overhead Rate Naranjo Company designs industrial prototypes for outside companies. Budgeted...

Job Costs Using a Plantwide Overhead Rate

Naranjo Company designs industrial prototypes for outside companies. Budgeted overhead for the year was $455,000, and budgeted direct labor hours were 26,000. The average wage rate for direct labor is expected to be $35 per hour. During June, Naranjo Company worked on four jobs. Data relating to these four jobs follow:

Job 39 Job 40 Job 41 Job 42
Beginning balance $23,600 $32,400 $18,400 $900
Materials requisitioned 18,600 21,800 12,800 14,600
Direct labor cost 9,700 18,900 7,450 5,500

Overhead is assigned as a percentage of direct labor cost. During June, Jobs 39 and 40 were completed; Job 39 was sold at 125 percent of cost. (Naranjo had originally developed Job 40 to order for a customer; however, that customer was near bankruptcy and the chance of Naranjo being paid was growing dimmer. Naranjo decided to hold Job 40 in inventory while the customer worked out its financial difficulties. Job 40 is the only job in Finished Goods Inventory.) Jobs 41 and 42 remain unfinished at the end of the month.

Required:

1. Calculate the balance in Work in Process as of June 30.

$

2. Calculate the balance in Finished Goods as of June 30.

$

3. Calculate the cost of goods sold for June.

$

4. Calculate the price charged for Job 39. Round your answer to the nearest cent.

$

5. What if the customer for Job 40 was able to pay for the job by June 30? What would happen to the balance in Finished Goods?

What would happen to the balance of Cost of Goods Sold?

In: Accounting

Job Costs Using a Plantwide Overhead Rate Naranjo Company designs industrial prototypes for outside companies. Budgeted...

Job Costs Using a Plantwide Overhead Rate

Naranjo Company designs industrial prototypes for outside companies. Budgeted overhead for the year was $270,000, and budgeted direct labor hours were 27,000. The average wage rate for direct labor is expected to be $20 per hour. During June, Naranjo Company worked on four jobs. Data relating to these four jobs follow:

Job 39 Job 40 Job 41 Job 42
Beginning balance $22,700 $32,200 $19,600 $200
Materials requisitioned 18,500 20,800 9,500 12,100
Direct labor cost 9,600 17,900 4,150 3,000

Overhead is assigned as a percentage of direct labor cost. During June, Jobs 39 and 40 were completed; Job 39 was sold at 115 percent of cost. (Naranjo had originally developed Job 40 to order for a customer; however, that customer was near bankruptcy and the chance of Naranjo being paid was growing dimmer. Naranjo decided to hold Job 40 in inventory while the customer worked out its financial difficulties. Job 40 is the only job in Finished Goods Inventory.) Jobs 41 and 42 remain unfinished at the end of the month.

Required:

1. Calculate the balance in Work in Process as of June 30.

$

2. Calculate the balance in Finished Goods as of June 30.

$

3. Calculate the cost of goods sold for June.

$

4. Calculate the price charged for Job 39. Round your answer to the nearest cent.

$

5. What if the customer for Job 40 was able to pay for the job by June 30? What would happen to the balance in Finished Goods?

What would happen to the balance of Cost of Goods Sold?

In: Accounting

Job Costs Using a Plantwide Overhead Rate Naranjo Company designs industrial prototypes for outside companies. Budgeted...

Job Costs Using a Plantwide Overhead Rate

Naranjo Company designs industrial prototypes for outside companies. Budgeted overhead for the year was $187,500, and budgeted direct labor hours were 15,000. The average wage rate for direct labor is expected to be $25 per hour. During June, Naranjo Company worked on four jobs. Data relating to these four jobs follow:

Job 39 Job 40 Job 41 Job 42
Beginning balance $25,500 $33,000 $17,500 $100
Materials requisitioned 18,300 20,800 11,200 15,700
Direct labor cost 9,400 17,900 5,850 6,600

Overhead is assigned as a percentage of direct labor cost. During June, Jobs 39 and 40 were completed; Job 39 was sold at 125 percent of cost. (Naranjo had originally developed Job 40 to order for a customer; however, that customer was near bankruptcy and the chance of Naranjo being paid was growing dimmer. Naranjo decided to hold Job 40 in inventory while the customer worked out its financial difficulties. Job 40 is the only job in Finished Goods Inventory.) Jobs 41 and 42 remain unfinished at the end of the month.

Required:

1. Calculate the balance in Work in Process as of June 30.

$

2. Calculate the balance in Finished Goods as of June 30.

$

3. Calculate the cost of goods sold for June.

$

4. Calculate the price charged for Job 39. Round your answer to the nearest cent.

$

5. What if the customer for Job 40 was able to pay for the job by June 30? What would happen to the balance in Finished Goods?

What would happen to the balance of Cost of Goods Sold?

In: Accounting

Problem 8-3A Asset cost allocation; straight-line depreciation LO C1, P1 [The following information applies to the...

Problem 8-3A Asset cost allocation; straight-line depreciation LO C1, P1

[The following information applies to the questions displayed below.]

In January 2017, Mitzu Co. pays $2,600,000 for a tract of land with two buildings on it. It plans to demolish Building 1 and build a new store in its place. Building 2 will be a company office; it is appraised at $644,000, with a useful life of 20 years and a $60,000 salvage value. A lighted parking lot near Building 1 has improvements (Land Improvements 1) valued at $420,000 that are expected to last another 12 years with no salvage value. Without the buildings and improvements, the tract of land is valued at $1,736,000. The company also incurs the following additional costs:

Cost to demolish Building 1 $ 328,400
Cost of additional land grading 175,400
Cost to construct new building (Building 3), having a useful life of 25 years and a $392,000 salvage value 2,202,000
Cost of new land improvements (Land Improvements 2) near Building 2 having a 20-year useful life and no salvage value 164,000

Problem 8-3A Part 3

3. Using the straight-line method, prepare the December 31 adjusting entries to record depreciation for the 12 months of 2017 when these assets were in use.

In: Accounting

what relationship building activities would you suggest a hotel manager beside relatioship marketing?

what relationship building activities would you suggest a hotel manager beside relatioship marketing?

In: Finance

Briefly discuss about heritage hotel in queenstown, nz (overview, marketing, staffing) in 1500 words

Briefly discuss about heritage hotel in queenstown, nz (overview, marketing, staffing) in 1500 words

In: Operations Management

What are the differences between a casino hotel and other types of hotels in terms of...

What are the differences between a casino hotel and other types of hotels in terms of the organization, facility, and management?

In: Operations Management

What are the challenges a US based hotel may face in the Greece because of its...

What are the challenges a US based hotel may face in the Greece because of its accounting standards?

In: Accounting

The Hotel Arcata faces a risk that it will suffer a fire causing a $ 200...

The Hotel Arcata faces a risk that it will suffer a fire causing a $ 200 million dollar loss with a probability of 0.02. The owner of the firm, Jackie Johnson, has a utility function of the form U(W) = W ½, where W is the owner’s wealth. The wealth is measured by the value of the hotel, which is $ 225 million dollars (i.e., W = 225).

A. What is Jackie Johnson’s expected loss?

B. What is Jackie Johnson’s expected utility?

C. What is Jackie Johnson’s risk premium?

In: Economics