In 2018, the Westgate Construction Company entered into a
contract to construct a road for Santa Clara County for
$10,000,000. The road was completed in 2020. Information related to
the contract is as follows:
| 2018 | 2019 | 2020 | |||||||
| Cost incurred during the year | $ | 2,072,000 | $ | 2,738,000 | $ | 2,849,000 | |||
| Estimated costs to complete as of year-end | 5,328,000 | 2,590,000 | 0 | ||||||
| Billings during the year | 2,160,000 | 2,650,000 | 5,190,000 | ||||||
| Cash collections during the year | 1,880,000 | 2,700,000 | 5,420,000 | ||||||
Westgate recognizes revenue over time according to percentage of
completion.
rev: 09_15_2017_QC_CS-99734
4. Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years assuming the following costs incurred and costs to complete information. (Do not round intermediate calculations and round your final answers to the nearest whole dollar amount. Loss amounts should be indicated with a minus sign.)
| 2018 | 2019 | 2020 | |||||||
| Cost incurred during the year | $ | 2,072,000 | $ | 3,880,000 | $ | 3,280,000 | |||
| Estimated costs to complete as of year-end | 5,328,000 | 3,180,000 | 0 | ||||||
In: Accounting
In 2018, the Westgate Construction Company entered into a
contract to construct a road for Santa Clara County for
$10,000,000. The road was completed in 2020. Information related to
the contract is as follows:
| 2018 | 2019 | 2020 | |||||||
| Cost incurred during the year | $ | 2,580,000 | $ | 4,042,000 | $ | 2,175,800 | |||
| Estimated costs to complete as of year-end | 6,020,000 | 1,978,000 | 0 | ||||||
| Billings during the year | 2,060,000 | 4,562,000 | 3,378,000 | ||||||
| Cash collections during the year | 1,830,000 | 4,200,000 | 3,970,000 | ||||||
Westgate recognizes revenue over time according to percentage of
completion
4. Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years assuming the following costs incurred and costs to complete information. (Do not round intermediate calculations and round your final answers to the nearest whole dollar amount. Loss amounts should be indicated with a minus sign.)
| 2018 | 2019 | 2020 | |||||||
| Cost incurred during the year | $ | 2,580,000 | $ | 3,830,000 | $ | 3,230,000 | |||
| Estimated costs to complete as of year-end | 6,020,000 | 3,130,000 | 0 | ||||||
In: Accounting
In 2018, the Westgate Construction Company entered into a
contract to construct a road for Santa Clara County for
$10,000,000. The road was completed in 2020. Information related to
the contract is as follows:
| 2018 | 2019 | 2020 | |||||||
| Cost incurred during the year | $ | 2,580,000 | $ | 4,042,000 | $ | 2,175,800 | |||
| Estimated costs to complete as of year-end | 6,020,000 | 1,978,000 | 0 | ||||||
| Billings during the year | 2,060,000 | 4,562,000 | 3,378,000 | ||||||
| Cash collections during the year | 1,830,000 | 4,200,000 | 3,970,000 | ||||||
Westgate recognizes revenue over time according to percentage of
completion.
rev: 09_15_2017_QC_CS-99734
4. Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years assuming the following costs incurred and costs to complete information. (Do not round intermediate calculations and round your final answers to the nearest whole dollar amount. Loss amounts should be indicated with a minus sign.)
| 2018 | 2019 | 2020 | |||||||
| Cost incurred during the year | $ | 2,580,000 | $ | 3,830,000 | $ | 3,230,000 | |||
| Estimated costs to complete as of year-end | 6,020,000 | 3,130,000 | 0 | ||||||
In: Accounting
In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2018 2019 2020 Cost incurred during the year $ 2,580,000 $ 4,042,000 $ 2,175,800 Estimated costs to complete as of year-end 6,020,000 1,978,000 0 Billings during the year 2,060,000 4,562,000 3,378,000 Cash collections during the year 1,830,000 4,200,000 3,970,000 Westgate recognizes revenue over time according to percentage of completion. rev: 09_15_2017_QC_CS-99734
5. Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years assuming the following costs incurred and costs to complete information. (Do not round intermediate calculations and round your final answers to the nearest whole dollar amount. Loss amounts should be indicated with a minus sign.)
2018 2019 2020 Cost incurred during the year $ 2,580,000 $ 3,830,000 $ 3,990,000 Estimated costs to complete as of year-end 6,020,000 4,160,000 0
In: Accounting
In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2018 2019 2020 Cost incurred during the year $ 2,580,000 $ 4,042,000 $ 2,175,800 Estimated costs to complete as of year-end 6,020,000 1,978,000 0 Billings during the year 2,060,000 4,562,000 3,378,000 Cash collections during the year 1,830,000 4,200,000 3,970,000 Westgate recognizes revenue over time according to percentage of completion. rev: 09_15_2017_QC_CS-99734 4. Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years assuming the following costs incurred and costs to complete information. (Do not round intermediate calculations and round your final answers to the nearest whole dollar amount. Loss amounts should be indicated with a minus sign.) 2018 2019 2020 Cost incurred during the year $ 2,580,000 $ 3,830,000 $ 3,230,000 Estimated costs to complete as of year-end 6,020,000 3,130,000 0
In: Accounting
In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2018 2019 2020 Cost incurred during the year $ 2,580,000 $ 4,042,000 $ 2,175,800 Estimated costs to complete as of year-end 6,020,000 1,978,000 0 Billings during the year 2,060,000 4,562,000 3,378,000 Cash collections during the year 1,830,000 4,200,000 3,970,000 Westgate recognizes revenue over time according to percentage of completion. rev: 09_15_2017_QC_CS-99734 4. Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years assuming the following costs incurred and costs to complete information. (Do not round intermediate calculations and round your final answers to the nearest whole dollar amount. Loss amounts should be indicated with a minus sign.) 2018 2019 2020 Cost incurred during the year $ 2,580,000 $ 3,830,000 $ 3,230,000 Estimated costs to complete as of year-end 6,020,000 3,130,000 0
In: Accounting
The cost of acquiring an asset includes the costs necessary to bring it to the condition and location necessary for its intended use. there are four stages during which costs can be incurred related to fixed assets:
· Preliminary stage,
· Pre-acquisition stage,
· Acquisition or construction stage (herein referred to as the construction stage),
· In-service stage
Please, provide a summary of some types of costs incurred during all stages of construction or acquisition of a capital asset/project. Discuss what sort of costs can be capitalized during each of the stages.
In: Accounting
Think about the last movie you saw in a movie theater. What aspects of the movie had international components in it? Are there more international elements included than compared to your favorite movie from 10 years ago?
In: Economics
Provide a definition of the following types of contracts, as it pertains to construction contracts:
Cost Plus Fee Contract
In: Civil Engineering
What are the best sources for labor and equipment unit prices to use in preparing construction cost estimates?
In: Operations Management